Projects / Case study 03 of 05 Completed 2025

Northern Link Road

A 7.4 km dual carriageway with 11 km of lined drains, three box culverts and two pedestrian bridges, built through two rainy seasons.

A public works agency / Kubwa, Abuja / 18 months

Aerial view of a town with buildings and roads
Client
A public works agency
Location
Kubwa, Abuja
Sector
Roads and drainage
Delivery
Employer's design, main contractor
Value band
₦6 billion to ₦9 billion
Duration
18 months
Floors
Not applicable
Size
7.4 km dual carriageway

The brief

Upgrade a single-lane road into a dual carriageway serving fast-growing residential districts, keep the existing road open throughout, and stop the seasonal flooding that cut the route every August.

How we built it

We resurveyed the catchment before we touched the road. Three of the culverts in the original design were undersized for the storms recorded since 2018; we raised it with the engineer and the box culverts were enlarged before construction.

Drains and culverts went in first, section by section, so the new formation was never left exposed to standing water. Traffic ran on one half-width while the other was built.

Our Idu yard materials laboratory tested every layer of sub-base and base course before the next one was placed, and asphalt was laid in a single season to avoid cold joints.

Outcome

Opened to traffic in March 2025. Through the 2025 rainy season the route stayed open every day, the first year that has happened in local memory.

The project in figures

km of dual carriageway
7.4
km of lined drains
11.2
box culverts, enlarged
3
pedestrian bridges
2
cubic metres of earthworks
46,000
tonnes of asphalt
18,500

Progress photographs

Select a photograph to enlarge it

  • Culvert units lifted in at chainage 3+250October 2023

  • Morning briefing before the half-width switchMay 2024

Key dates

From contract award to handover.

  1. 01Contract awardSeptember 2023
  2. 02Drainage completeJune 2024
  3. 03Base course completeNovember 2024
  4. 04Surfacing completeFebruary 2025
  5. 05Open to trafficMarch 2025