Headquarters fit-out, Central Business District
Six floors of a working headquarters fitted out one floor at a time, with staff moving in behind us.
A telecommunications operator / Central Business District, Abuja / 11 months
- Client
- A telecommunications operator
- Location
- Central Business District, Abuja
- Sector
- Fit-out
- Delivery
- Cat B fit-out, occupied building
- Value band
- ₦3 billion to ₦5 billion
- Duration
- 11 months
- Floors
- 6 floors fitted
- Size
- 9,200 sqm
The brief
Fit out six office floors and a customer experience centre for 840 staff while the operator's network operations centre stays live on level 2. Every floor must be finished before its team moves in, on a fixed sequence agreed with the client's HR team.
How we built it
We built a full sample bay on level 5, from raised floor to joinery and lighting, and the client signed it off before any floor started. Every subsequent floor is inspected against that bay.
Noisy and dusty work runs from 18.00 to 06.00 and at weekends, with lifts protected and common areas cleaned before staff arrive. The network operations centre has its own isolation plan.
Furniture, AV and data are installed by our team, so each floor hands over complete on a Friday and is occupied on the Monday.
Outcome
Four of six floors are complete and occupied. The customer experience centre and final floor are on programme for completion in February 2027.
The project in figures
- workstations
- 840
- floors, phased
- 6
- complete, November 2026
- 68%
- meeting rooms
- 42
- unplanned outages to the live operations centre
- 0
- floor handed over every 6 weeks
- 1
Progress photographs
Select a photograph to enlarge it
-
Level 5 sample bay layout, approved revisionApril 2026
-
Timber flooring going down in the level 4 loungeSeptember 2026
Key dates
From contract award to planned completion.
- 01Contract awardMarch 2026
- 02Sample bay approvedMay 2026
- 03Levels 3 and 4 occupiedAugust 2026
- 04Levels 5 and 6 occupiedNovember 2026, planned
- 05CompletionFebruary 2027, planned