Projects / Case study 04 of 05 In progress, 68% complete

Headquarters fit-out, Central Business District

Six floors of a working headquarters fitted out one floor at a time, with staff moving in behind us.

A telecommunications operator / Central Business District, Abuja / 11 months

A site manager marking up a printed plan
Client
A telecommunications operator
Location
Central Business District, Abuja
Sector
Fit-out
Delivery
Cat B fit-out, occupied building
Value band
₦3 billion to ₦5 billion
Duration
11 months
Floors
6 floors fitted
Size
9,200 sqm

The brief

Fit out six office floors and a customer experience centre for 840 staff while the operator's network operations centre stays live on level 2. Every floor must be finished before its team moves in, on a fixed sequence agreed with the client's HR team.

How we built it

We built a full sample bay on level 5, from raised floor to joinery and lighting, and the client signed it off before any floor started. Every subsequent floor is inspected against that bay.

Noisy and dusty work runs from 18.00 to 06.00 and at weekends, with lifts protected and common areas cleaned before staff arrive. The network operations centre has its own isolation plan.

Furniture, AV and data are installed by our team, so each floor hands over complete on a Friday and is occupied on the Monday.

Outcome

Four of six floors are complete and occupied. The customer experience centre and final floor are on programme for completion in February 2027.

The project in figures

workstations
840
floors, phased
6
complete, November 2026
68%
meeting rooms
42
unplanned outages to the live operations centre
0
floor handed over every 6 weeks
1

Progress photographs

Select a photograph to enlarge it

  • Level 5 sample bay layout, approved revisionApril 2026

  • Timber flooring going down in the level 4 loungeSeptember 2026

Key dates

From contract award to planned completion.

  1. 01Contract awardMarch 2026
  2. 02Sample bay approvedMay 2026
  3. 03Levels 3 and 4 occupiedAugust 2026
  4. 04Levels 5 and 6 occupiedNovember 2026, planned
  5. 05CompletionFebruary 2027, planned