Eight stages, from tender to handover.
The programme below is a typical 20-floor residential tower. Every stage has a named lead and a set of documents you receive before the next one starts.
- 01 Tender and estimate 2 to 6 weeks
- 02 Pre-construction 4 to 10 weeks
- 03 Mobilisation 2 to 4 weeks
- 04 Substructure 3 to 8 months
- 05 Superstructure and envelope 8 to 20 months
- 06 Services and finishes 6 to 14 months
- 07 Testing and commissioning 4 to 10 weeks
- 08 Handover and defects 12 months
01
Tender and estimate
2 to 6 weeks / led by estimating team
We read every drawing, visit the site, price from first principles and return a tender with a programme, a method statement and the risks we see. If something in the documents does not add up, we say so in writing.
You receive
- Priced bill of quantities
- Tender programme
- Method statement and logistics plan
- Clarifications and risks list
02
Pre-construction
4 to 10 weeks / led by project manager
Before the hoarding goes up we finalise the programme, procure long-lead items, set up the site management plan and agree the inspection and test plan with your engineer.
You receive
- Contract programme
- Procurement schedule
- Construction phase safety plan
- Inspection and test plan
03
Mobilisation
2 to 4 weeks / led by site manager
Hoarding, site offices, welfare, power, water and the tower crane base. Neighbours receive a letter with our site manager's phone number on the first day.
You receive
- Site set up and inducted
- Neighbour letters
- Crane and hoist installed
04
Substructure
3 to 8 months / led by engineering director
Piling, excavation, retaining walls, basements and foundations. Survey and settlement monitoring run daily, and every pour is witnessed and cube-tested.
You receive
- Pile test records
- Monitoring reports
- Basement handover to frame team
05
Superstructure and envelope
8 to 20 months / led by frame and façade managers
Core, slabs and columns on a weekly cycle, with envelope following a set number of floors behind. You receive a dated photo record every week.
You receive
- Weekly progress report with photos
- Concrete test register
- Façade water-test records
06
Services and finishes
6 to 14 months / led by services manager
Mechanical, electrical and plumbing installation, lifts and finishes, with a sample area signed off by you before any repetition starts.
You receive
- Approved sample area
- Room-by-room inspection sheets
07
Testing and commissioning
4 to 10 weeks / led by commissioning engineer
Every system is tested, balanced and witnessed: generators, lifts, fire alarm, pumps, cooling and building management.
You receive
- Witnessed test certificates
- Commissioning reports
08
Handover and defects
12 months / led by project manager and aftercare team
We hand over with as-built drawings, manuals and training for your facilities team, then stay for a 12-month defects period with a named aftercare manager.
You receive
- As-built drawings
- Operation and maintenance manuals
- Facilities team training
- Defects log closed out
Every Friday, a report you can read in ten minutes.
From mobilisation to handover, the project manager sends the same four-page report at the end of every week. Nothing in it needs a quantity surveyor to translate.
- Page 1
Programme
Planned against actual for every activity this week and next, with any slippage and the plan to recover it.
- Page 2
Photographs
Twelve dated photographs from fixed points around the site, so you can compare week with week.
- Page 3
Cost
Committed cost, variations agreed and pending, and the forecast final account.
- Page 4
Safety and quality
Hours worked, near misses reported, inspections passed and any non-conformances raised.
Stage one starts with your drawings or a brief.