Fabrication
Skids, spools, structures and process modules, built under cover at Onne and loaded straight onto a barge at our own quay.
- Service code
- FB
- Yard at Onne
- 4.2 ha
- Fabricated since 2014
- 18,600 t
- Load-out quay rating
- 400 t
Scope
Our Onne yard runs two covered fabrication halls, a pipe shop, a blast and paint facility and a load-out quay. We fabricate to the operator's drawings or to our own detailed design.
- Process and utility modules up to 650 tonnes
- Piping spools in carbon steel, stainless and duplex
- Platform structures, launchers, receivers and skids
- Blast and paint to offshore coating systems
- Load-out by self-propelled modular transporter to barge
Black and grey pipework close up. Deltaline fabrication, illustrative photograph.
Capabilities
What we bring to site, in plain terms. Specifications and certificates for any item are shared with operators at tender stage.
Covered halls
Two halls totalling 5,600 square metres, with 40-tonne and 25-tonne overhead cranes.
Pipe shop
Bevelling, bending and automatic orbital welding for spools from 2 in to 36 in.
Coating
An enclosed blast room and a climate-controlled paint shop with humidity and dew point logging.
Load-out
A 180 metre quay with a 400-tonne rated load-out zone and SPMT hire arranged through our yard.
Key equipment
Owned by Deltaline and maintained at Onne. The full register is on the fleet and equipment page.
Fleet and equipment| Item | Specification | Qty |
|---|---|---|
| Overhead crane | 40 t, 32 m span | 2 |
| Crawler crane | 250 t | 1 |
| Orbital welding head | TIG, 2 in to 12 in | 6 |
| Plate rolling machine | 3 m width, 40 mm | 1 |
| CNC plasma cutting table | 3 m by 12 m | 1 |
| Blast room | 24 m by 8 m | 1 |
How a typical project runs
Durations are typical for a mid-sized scope. Every programme is agreed with the operator before mobilisation.
Drawings and materials
2 weeksDrawings checked, material take-off reconciled and mill certificates verified on receipt.
Inspection and test plan
1 weekAn ITP agreed with the operator, with hold and witness points marked before cutting starts.
Fabrication
By weightCut, fit, weld and inspect. Daily progress against the weld log is shared with the client.
Coating and testing
2 to 4 weeksBlast, paint and hydrotest. Every coat is measured and recorded.
Load-out
1 to 3 daysWeighing, sea-fastening design and load-out to barge at our quay, with the marine warranty surveyor present.
Work in this discipline
| Ref | Year | Scope | Result |
|---|---|---|---|
| DL-FB-2246 | 2025 | Pig launcher and receiver skids, 16 in | Delivered 9 days early |
| DL-FB-2196 | 2024 | Platform boat landing and riser guards | Installed in one weather window |