Well services
We put crews, coiled tubing and slickline on wells that need attention, and we bring them back into production or close them out properly.
- Service code
- WS
- Well entries since 2009
- 640
- Wells plugged and abandoned
- 38
- First-run success, 2025
- 96.4%
Scope
Our well services crews work from swamp barges, lift boats and land locations across the Niger Delta. Every job starts from the well file, not from the equipment we happen to have free.
- Rigless well intervention: slickline, e-line and coiled tubing
- Workover and recompletion support on land and swamp wells
- Wellhead and christmas tree maintenance, valve servicing and greasing
- Plug and abandonment programmes, from design to final cement verification
- Well testing and clean-up with temporary surface facilities
A white and grey rig structure in daylight. Deltaline well services, illustrative photograph.
Capabilities
What we bring to site, in plain terms. Specifications and certificates for any item are shared with operators at tender stage.
Coiled tubing
Two 1.75 in units rated to 10,000 psi, with nitrogen pumping and fluid spreads on skids for barge work.
Slickline and e-line
Six slickline units and two e-line units with memory and surface readout gauges, gauge cutting and fishing tools.
Swamp access
Barge-mounted spreads that reach wells in mangrove locations where a land rig cannot, with crew quarters on board.
Abandonment
Plug design, cement placement and pressure testing, documented to the standard the regulator and the operator both expect.
Key equipment
Owned by Deltaline and maintained at Onne. The full register is on the fleet and equipment page.
Fleet and equipment| Item | Specification | Qty |
|---|---|---|
| Coiled tubing unit, 1.75 in | 10,000 psi, 18,000 ft reel | 2 |
| Nitrogen pumping unit | 180,000 scf/h | 2 |
| Slickline unit, skid mounted | 0.108 in and 0.125 in wire | 6 |
| E-line unit | 7-conductor, 25,000 ft | 2 |
| Well test separator | 3-phase, 1,440 psi | 1 |
| Cementing unit, twin pump | 15,000 psi | 1 |
How a typical project runs
Durations are typical for a mid-sized scope. Every programme is agreed with the operator before mobilisation.
Well file review
Week 1We read the completion history, last pressure surveys and any integrity flags, then agree the objective with the operator's well engineer.
Programme and risk review
Week 2A written programme, a hazard identification session with the operator, and a barrier plan signed by both sides.
Mobilisation
Week 3Equipment is tested at Onne, loaded out and moved by barge or road. Crew competence is checked against the programme.
Execution
5 to 21 daysTwelve-hour shifts, a daily report before 06:00, and a stop point at every barrier change.
Close-out
2 weeksFinal well status, as-run diagrams and a lessons log, delivered within ten working days of demobilisation.
Work in this discipline
| Ref | Year | Scope | Result |
|---|---|---|---|
| DL-WS-2251 | 2025 | Plug and abandonment of four swamp wells | All plugs verified first time |
| DL-WS-2214 | 2024 | Wellhead maintenance on 63 land wells | Completed under budget |