A 540 tonne compression module, fabricated and loaded out at Onne
- Reference
- DL-FB-2265
- Service line
- FB
- Duration
- 11 months
- Year
- 2025 to 2026
A gas compression module built entirely in Nigeria, from steel receipt to sea-fastened load-out.
Scope
- Structural steel and three-level module frame
- Process and utility piping in carbon and stainless steel
- Equipment setting: two compressor packages and coolers
- Electrical and instrument installation and pre-commissioning
- Load-out to barge and sea-fastening at our quay
The challenge
The operator had built its previous modules overseas. This was the first time it would rely on a Nigerian yard for a module of this size, and the installation date was fixed by a gas supply agreement.
Long-lead compressor packages arrived seven weeks late.
Our approach
Build around the late equipment
We re-sequenced the module so piping and structure on the upper levels were completed first, leaving clear access to set the compressors when they arrived.
Witness points the client could reach
The operator's inspectors had a desk in our yard office and a live ITP tracker, so no hold point waited for travel.
Load-out at our own quay
The module rolled onto the barge on self-propelled transporters at our 400 tonne quay, avoiding a road move.
-
Fig. 1. A group of connected pipes and valves. Select to enlarge.
-
Fig. 2. Polished pipework catching warm light. Select to enlarge.
Project figures
- Dry weight
- 540 t
- Footprint
- 32 m by 18 m
- Structural steel
- 212 t
- Piping welds
- 2,860
- Weld repair rate
- 1.1%
- Manhours
- 396,000
- Lost-time injuries
- 0
- Delay recovered against equipment slip
- 5 of 7 weeks
Timeline
- Feb 2025
Award
Contract signed, steel ordered from a Nigerian mill and two importers.
- Apr 2025
First steel cut
Module frame started in Hall 2.
- Sep 2025
Compressors set
Late packages lifted in through the open upper levels.
- Dec 2025
Pre-commissioning
Loop checks, flushing and pressure testing completed.
- Jan 2026
Load-out
Module loaded out and sea-fastened at the Onne quay.
We will build the next one here as well.