A 540 tonne compression module, fabricated and loaded out at Onne

Reference
DL-FB-2265
Service line
FB
Duration
11 months
Year
2025 to 2026
540 tmodule dry weight
2,860piping welds
100%fabricated in Nigeria

A gas compression module built entirely in Nigeria, from steel receipt to sea-fastened load-out.

Scope

  • Structural steel and three-level module frame
  • Process and utility piping in carbon and stainless steel
  • Equipment setting: two compressor packages and coolers
  • Electrical and instrument installation and pre-commissioning
  • Load-out to barge and sea-fastening at our quay

The challenge

The operator had built its previous modules overseas. This was the first time it would rely on a Nigerian yard for a module of this size, and the installation date was fixed by a gas supply agreement.

Long-lead compressor packages arrived seven weeks late.

Our approach

Build around the late equipment

We re-sequenced the module so piping and structure on the upper levels were completed first, leaving clear access to set the compressors when they arrived.

Witness points the client could reach

The operator's inspectors had a desk in our yard office and a live ITP tracker, so no hold point waited for travel.

Load-out at our own quay

The module rolled onto the barge on self-propelled transporters at our 400 tonne quay, avoiding a road move.

  • Fig. 1. A group of connected pipes and valves. Select to enlarge.

  • Fig. 2. Polished pipework catching warm light. Select to enlarge.

Project figures

Dry weight
540 t
Footprint
32 m by 18 m
Structural steel
212 t
Piping welds
2,860
Weld repair rate
1.1%
Manhours
396,000
Lost-time injuries
0
Delay recovered against equipment slip
5 of 7 weeks

Timeline

  1. Feb 2025

    Award

    Contract signed, steel ordered from a Nigerian mill and two importers.

  2. Apr 2025

    First steel cut

    Module frame started in Hall 2.

  3. Sep 2025

    Compressors set

    Late packages lifted in through the open upper levels.

  4. Dec 2025

    Pre-commissioning

    Loop checks, flushing and pressure testing completed.

  5. Jan 2026

    Load-out

    Module loaded out and sea-fastened at the Onne quay.

We will build the next one here as well.

Head of projects, operator's gas development