28 October 2026. 7 minute read.
Buying off-plan in Lagos: what your contract should say
Seven clauses to look for before you pay a deposit on a home that does not exist yet.
By Olumide Fashola, chief financial officer
Off-plan buying has a poor reputation in Lagos, and some of it is earned. Buyers have paid for towers that stalled at the fourth floor, or received keys to homes that bore little resemblance to the brochure. Yet buying early is still the best way to secure a good residence at a fair price. The difference between a sound purchase and a painful one is almost always in the contract.
Here is what we think every off-plan contract should contain. We put all seven in ours, and we encourage buyers to have their own lawyer check them.
1. Where your money goes
Your deposit and instalments should go into an escrow or project account that is separate from the developer's general funds, with withdrawals tied to verified construction milestones. Ask who controls the account and who certifies each release.
2. A fixed price
The contract should state that the price agreed is the price paid. Clauses allowing the developer to pass on cost increases, exchange rate movements or new taxes can add a great deal to your final bill.
3. A completion date with consequences
A target date is not enough. Look for a long-stop date after which you can withdraw and recover your money, and a compensation rate for each month of delay.
4. A specification schedule
The finishes, appliances and services should be listed in a schedule attached to the contract, with a clause stating that any substitute must be of equal or better quality and agreed with you in writing.
5. Title and consent
Ask to see the root of title and the building approval. For a sectional title in Lagos, you should know how and when your own Governor's Consent will be processed, and who pays for it.
6. Service charge, before you buy
A budget for the first year's service charge should be shared before you sign, along with how it will be set in later years. A surprisingly high service charge is the most common complaint we hear about other buildings.
7. A defects period
We hold back 5% of every contractor's fee for a year after handover. It is the simplest way to make sure snags are fixed.
Your contract should give you at least twelve months after handover in which the developer must fix defects at no cost. Ask how defects are reported and how quickly they are put right.
None of this should be unusual. If a developer resists any of these points, ask why. A good project has nothing to lose by putting its promises in writing.